New home for the School of Property Construction and Project Management (PCPM) staff in Building 8, Level 8

New student lounge for the School of Property, Construction and Project Management.
- Address
- Project overview
- Project update
- Project update: staff and student access
- Project timeline
- Consultants
- Construction of an informal student lounge and study space
- Refurbished administrative and office areas
- Three new teaching spaces – each with a capacity to seat between 50 and 70 people
- Enlargement and refurbishment of current teaching space, which will be modified to
- include a section of existing administration offices.
- Upgrade of all workstation furniture in the administrative / office areas that were refurbished as part of Stage 1.
- Upgrade and modernise two entry points into the School
- Refurbish large outdoor balcony area, which will include shelter, seating, plants and rock gardens, and lighting
- New flooring material to be installed throughout the School
- Major mechanical upgrade to service teaching spaces
- New data room to accommodate new data rack
Address
360 Swanston Street, City
Project overview
Staff in the School of Property Construction and Project Management (PCPM) are being relocated from Building 101, on the corner of La Trobe and Russell Streets into the eighth level of Building 8, in the heart of the City campus, which is being refurbished to accommodate the School’s diverse needs. There are two stages in the project.
Stage 1
Stage 2
Project update
September – December 2009
The tender for the main contractor (construction company) closed on 13th November with McCormack being appointed. Construction works began in late November with works set to finish in February, 2010, in time for first semester.
May – August 2009
Schematic design for Stage 2 has been completed and detailed design is due for completion in mid-September. The tender for the main contractor will be issued shortly after the detailed design is finished.
April 2009
Building 8, Level 8 Stage 1 refurbishments are now complete and the School of PCPM staff are moving into their new premises.
March 2009
The contractor – ISIS Projects – has been appointed for building works and construction commenced in late March.
Project timeline
|
Work begins |
Stage 1 March 2009 Stage 2 June 2009 |
|
Work ends |
Stage 1 April 2009 Stage 2 Late February, 2010 |
Consultants
|
RMIT Project Manager | |
|
RMIT Manager, Client Relations | |
|
Services Engineer |
O’Connor Associates |
|
Building Surveyor |
BGSM |
|
Quantity Surveyor |
Prowse Quantity Surveyors |
|
Architect |
Payne Pattenden |
|
Main Contractor |
ISIS Projects (Stage 1) |
|
Main Contractor |
McCormack (Stage 2) |